In DBB, which is typically selected first?

Prepare for the DBIA Exam with our practice test. Study with engaging flashcards and multiple-choice questions, complete with hints and explanations. Excel in your exam prep!

Multiple Choice

In DBB, which is typically selected first?

Explanation:
In a DBB project, design and construction are handled as separate contracts. The owner hires the architect-engineer first to develop the complete design and the bid-ready documents. Only after that design is sufficiently defined are bids invited and a general contractor selected based on those bids. This sequencing ensures a defined scope and price for bidding and keeps design and construction activities independent. Choosing the architect-engineer first best reflects how DBB projects are typically procured.

In a DBB project, design and construction are handled as separate contracts. The owner hires the architect-engineer first to develop the complete design and the bid-ready documents. Only after that design is sufficiently defined are bids invited and a general contractor selected based on those bids. This sequencing ensures a defined scope and price for bidding and keeps design and construction activities independent. Choosing the architect-engineer first best reflects how DBB projects are typically procured.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy