Which DB type is described as the predominant approach used by the public sector?

Prepare for the DBIA Exam with our practice test. Study with engaging flashcards and multiple-choice questions, complete with hints and explanations. Excel in your exam prep!

Multiple Choice

Which DB type is described as the predominant approach used by the public sector?

Explanation:
Public sector projects have historically used a design-bid-build approach, where design and construction are separate and the owner first hires a designer and then awards a distinct construction contract based on competitive bids. This separation aligns with public procurement standards—transparency, competition, and clear liability—making it the predominant delivery method in government projects. Other delivery methods exist and are used in various contexts (for example, design-build or CM at risk can accelerate schedules or improve collaboration), but they have not been the dominant approach in the public sector.

Public sector projects have historically used a design-bid-build approach, where design and construction are separate and the owner first hires a designer and then awards a distinct construction contract based on competitive bids. This separation aligns with public procurement standards—transparency, competition, and clear liability—making it the predominant delivery method in government projects. Other delivery methods exist and are used in various contexts (for example, design-build or CM at risk can accelerate schedules or improve collaboration), but they have not been the dominant approach in the public sector.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy